Location: Brecon Street, Queenstown
Contract Value: $344,314.21
Project Completion Date: April 2011
Company: GHD Queenstown

For this project we pre milled and reshaped 2300m2 of Brecon Street, and then completed foam bitumen stabilization on the main carriage way and on the smaller parking bays we completed cement stabilization. During the pre mill and reshape process we reshaped the existing carriageway ensuring we maximized all the onsite material prior to carting the excess waste offsite. This work was completed at night time with the intention of having the minimum possible impact on the surrounding businesses. This also allowed us to close the road to non essential traffic and detour it around the site. Completing this work at night time was very challenging but we believe in the end resulted in the client getting a higher quality end product.

BrECON STREET UPGRADE